Infrastructure:Incident 2015-04-23

From the Linux and Unix Users Group at Virginia Teck Wiki
Revision as of 03:02, 24 April 2015 by imported>Mutantmonkey (Created page with "In the early morning of April 23, 2015, Whittemore lost power and brought down VTLUUG infrastructure. Issues bringing hardware back up were compounded by: * Maintenance deferr...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

In the early morning of April 23, 2015, Whittemore lost power and brought down VTLUUG infrastructure. Issues bringing hardware back up were compounded by:

  • Maintenance deferred for far too long, which prevented some machines from booting on their own.
  • Failure to notice the clocks on VMs were wrong due to a dead CMOS battery on wood, which prevented Kerberos from working properly.
  • Lack of a dedicated sysadmin with the time and experience necessary to correct these problems.
  • Lack of a disaster recovery plan.

Some steps that should be taken to reduce the length and impact of future outages include:

  • Rebuild VMs like milton, which have had too much maintenance deferred, and move them to cyberdelia.
  • Install NTP on all servers.
  • Find a dedicated sysadmin.
  • Create a disaster recovery plan.